Bitwarden runs cross-cutting technical work through the Software Initiative Funnel. A senior engineer — typically Staff+ for cross-team initiatives, sometimes a tech lead for smaller-scope work that lives largely inside one team's domain — shepherds each initiative through five phases: Identification, Research, Proof of Concept, Scoping & Commitment, and Implementation. The tech lead participates throughout, but most heavily in Scoping & Commitment and Implementation. This skill is the working playbook for that participation, written from the perspective of a tech lead working alongside a separate shepherd; when the tech lead is also shepherding the initiative, read the phase descriptions for both roles and run both. When the canonical reference is needed, fetch the funnel page via the get_confluence_page MCP tool; this document is the operating summary.
The Rule of Ownership
Every phase has a single sentence to remember: the shepherd owns the initiative; the tech lead owns how their team executes its part. The moment that line blurs, one of two failure modes shows up — either the shepherd starts writing the team's stories (and the team doesn't own the work), or the tech lead starts making cross-team decisions that aren't theirs to make (and the initiative drifts).
Phase-by-Phase: Who Does What
Phase 1 — Identification
The shepherd creates a BW Initiative issue, documents the problem, and gets a go/no-go from engineering leadership.
The tech lead's role is light here. If the shepherd reaches out because the team's domain is affected, provide context, known history, and stakeholders. Flag prior attempts. Don't pre-scope — the research hasn't happened yet.
Phase 2 — Research
The shepherd interviews stakeholders (the tech lead is a likely one), surveys the codebase, and produces an Architectural Assessment with 2–4 solution options.
The tech lead's role: be interviewed well. Share the team's pain points, workarounds, and the constraints the shepherd won't see from outside. Quantify where possible ("this causes ~3 bugs per sprint"). If the shepherd proposes a direction that would conflict with work already on the team's roadmap, surface it now — not after commitment.