Program management
Programs fail at the seams between teams, not inside them. The job is the seams.
Set up
- One outcome, stated as a business result with a date. Programs with several equal objectives have none.
- A named accountable owner — one person, not a committee. The program manager drives; the owner decides.
- Scope written as inclusions and exclusions. The exclusions do the work; unwritten exclusions return as assumptions.
- Dependencies mapped and agreed by the teams that owe them, with dates they have actually committed to. A dependency in your plan that the owning team has not agreed to is a wish.