Delivery Schedule — triple productivity (P100 / P85 / P50)

Produce one delivery-schedule markdown for a version (or remaining slices): three productivity scenarios, each with PERT phases + Monte Carlo calendar percentiles.

Not commercial FP quoting (ns-commercial-budget). Not story-level forecast alone (ns-project-manager Phase 5). Never invent R$.

Critical naming (never conflate)

Label Meaning
Productivity scenario P100 Today's real productivity (baseline) — h_fp = produtividade_atual
Productivity scenario P85 Goal: 50% fasterh_fp = produtividade_atual × 0.50
Productivity scenario P50 Goal: 85% fasterh_fp = produtividade_atual × 0.15
Delivery percentiles P50 / P85 / P95 Monte Carlo calendar outcomes inside each productivity scenario

P100 = reality. P85 and P50 productivity scenarios = acceleration goals, not Monte Carlo percentiles.

Faster formula: horas_novas = horas_atuais × (1 − X/100) → 50% faster ⇒ ×0.50; 85% faster ⇒ ×0.15.