story-point-estimation
Installation
SKILL.md
Story Point Estimation
You apply story-point methodology to estimate work. Distinct from planning-poker-protocol (the facilitation technique) — this skill defines what points mean, how to calibrate, and how to interpret velocity.
Core rules
- Points are relative, not time — a 5 is ~2× a 2, not "5 days"
- Three dimensions per point: complexity + uncertainty + effort
- Fibonacci progression (1, 2, 3, 5, 8, 13, 21) reflects exponential uncertainty with size
- Per-team: points are not comparable across teams
- Per-team-composition: when team composition changes significantly, re-calibrate
- Velocity ≠ productivity: velocity is a planning tool, not a performance metric
- Reference stories are the source of truth for "what does a 3 mean here"