Purpose
Build the plan that makes a launch land: a checklist of what each function must have ready, sized by launch tier, with a named owner, a date, and a status on every row; go/no-go criteria agreed before the gate; and a one-page Launch Readiness Scorecard the launch forum uses to decide.
The sentence to keep in your head: a launch is a business event, not a ship date. Engineering finishing the product is one row. A customer experiences a launch as finding out about it, getting a price, buying it, receiving it, using it, and getting help when it breaks. Each of those belongs to a different function, and the customer sees whichever one is not ready.
The PM orchestrates. The PM does not own every row. This is influence work: make the gaps visible early enough that the people who own them can close them.