Change Order Writer Skill
A change order that just says "extra work — $48,500" gets cut in half in review. A defensible one answers three questions before they're asked: why am I entitled (which contract clause, triggered by what event), what exactly changed (scope delta from the contract baseline), and what does it really cost (built-up pricing plus time). This skill drafts change orders that survive an owner's rep audit — and preserves rights on the impacts you can't price yet.
What This Skill Produces
- A complete change order request (COR/PCO) ready for letterhead
- Entitlement narrative citing the contract clause and the triggering event/document
- Scope delta — contract baseline vs. changed condition, with document references
- Pricing breakdown: labour, material, equipment, subcontractor cost, then OH&P per the contract markup provisions
- Schedule impact statement and a reservation of rights for cumulative/unquantified impacts
Required Inputs
Ask for what's missing; from a thin brief, draft anyway and mark every gap [confirm]: